TL;DR: From 2030, the Maritime and Port Authority of Singapore (MPA) requires every new harbour craft operating in Singapore to be fully electric, capable of running on B100 biofuel, or compatible with net-zero fuels such as hydrogen. The rule is aimed at new craft, so existing diesel boats are not forced off the water in 2030, but the whole sector is expected to reach net zero by 2050. Owners renewing a fleet between now and 2030 should decide which of the three pathways each craft type can realistically take, check charging access, and look at the Early Adopter Scheme for Electric Harbour Craft (EASE) grant that opens on 1 January 2027.
Harbour craft are the working boats of the Port of Singapore: launches, lighters, tugs, bunker tankers and water boats. MPA puts the sector at more than 1,600 craft, predominantly diesel-powered. The boats being specified, financed and built today are the ones the 2030 rule will catch, and this guide is for the owners and fleet managers making those calls.
What does MPA’s 2030 requirement actually say?
From 2030, all new harbour craft operating in Singapore must be fully electric, capable of using B100 biofuel, or compatible with net-zero fuels. MPA restated this in its October 2026 announcement of the EASE grant, alongside the expectation that the sector reaches net zero by 2050.
That gives owners three compliance routes, not one:
Full electric, meaning battery-powered propulsion charged from shore or by battery swap.
B100-capable, meaning engines and fuel systems that can run on 100% biofuel rather than a blend.
Net-zero fuel compatible, with hydrogen named as an example.
The requirement was first set out in March 2023. At the time, Ship & Bunker reported that MPA wanted owners to pre-consult it on vessel designs no later than January 2027 for craft coming into service in 2030. Treat that date as a planning signal and confirm the current process directly with MPA before you commit to a design.
One point owners keep asking about is what “new” covers. The published wording speaks of new harbour craft operating in Singapore. Whether that captures a second-hand boat brought in from overseas and licensed for the first time after 2030 is a question to put to MPA in writing for your specific case, not something to assume.

Which harbour craft are covered?
The requirement applies to harbour craft, which in Singapore means commercial vessels licensed by MPA to operate within port limits. MPA licenses harbour craft by category: SB for craft carrying bulk liquids (bunker tankers sit here), SC for dry or packaged cargo, SP for passengers, ST for tugs, and SR for other purposes.
The categories matter because duty cycles differ. A passenger launch running short legs to the anchorage, with time alongside between trips, suits batteries. A bunker tanker runs cargo pumps for hours and may make several deliveries a day. A tug needs high peak power on demand. Same rule, very different engineering answer.
How the three compliance pathways compare
The quickest way to see the trade-off is side by side. The table below is our reading of how each route affects an owner, based on MPA’s published requirement and what we see in craft operations.
Factor | Full electric | B100-capable | Net-zero fuel (e.g. hydrogen) |
|---|---|---|---|
Fits best | Short, repeatable routes with time alongside (launches, some lighters) | Higher-endurance or high-power duty (bunker tankers, tugs) | Early pilots; limited commercial supply today |
Main dependency | Charging access and grid capacity at your base | Engine maker approval and reliable B100 supply | Fuel availability, storage and safety rules |
Capex pattern | High upfront (battery system) | Closer to conventional newbuild | Highest uncertainty |
Maintenance change | Battery health, thermal management, high-voltage systems | Fuel stability, filters, seals and tank hygiene | New fuel systems and gas detection |
Grant support | EASE covers part of battery cost (from 2027) | Not covered by EASE | Not covered by EASE |
The grant row is fact; the rest is interpretation, and an owner’s naval architect and engine maker should test it against each specific design.
Where charging infrastructure stands
Shore charging in Singapore is still being built out, so access at your operating base is the first thing to check before choosing electric. MPA opened its first pilot electric harbour craft charger at Marina South Pier in April 2024: a 150 kW DC fast charger with a CCS2 connector, run by a partnership of Pyxis Energy, Pyxis Maritime and SP Mobility. MPA said it could fully charge a battery of about 500 kWh in around three hours, giving roughly 50 nautical miles of range.
As of MPA’s October 2026 update, a second charger at Marina South Pier is due in the coming months, four chargers are planned for Loyang Offshore Supply Base, and public chargers are planned for Jurong Port and West Coast Pier in 2027. MPA is also studying battery-based and mobile chargers, and running studies at key terminals on power capacity upgrades.
On 25 March 2025, the Singapore Standards Council, Enterprise Singapore and MPA published Technical Reference 136 (TR 136), which sets safety requirements for electric harbour craft (e-HC) charging infrastructure and battery swap systems and promotes interoperability. It builds on widely used electric-vehicle charging standards such as the Combined Charging System, and references TR 25, IEC 61851 and IEC 62840. The practical point for an owner: specify a charging interface that follows TR 136, so the craft can use public chargers and not only your own.
What support is on offer
There are three forms of support an owner can plan around today.
The first is the EASE grant. It starts on 1 January 2027 and runs for two years. It covers part of the battery system cost of an eligible electric harbour craft, scaled to battery capacity, capped by vessel size, and up to S$250,000 per vessel. Eligibility criteria sit in an annex to MPA’s release, so read those before you build a business case around the full amount.
The second is financing. In April 2024 MPA said harbour craft owners could take loans with 70% risk-sharing by Enterprise Singapore under the expanded Enterprise Financing Scheme-Green (EFS-Green), and it shortlisted five banks for direct debt financing proposals.
The third is insurance clarity. MPA reported in April 2024 that the insurance proposals it received indicated premiums for electric harbour craft comparable to conventional craft. That was an indication from proposals, not a market rate, so get your own quotes.
Retrofit or replace: how owners should think about it
For most owners, the 2030 rule is a newbuild question first and a retrofit question second. Existing craft are not caught by the published 2030 wording, so the pressure point is the timing of each boat’s replacement.
Our view is that the decision should be made boat by boat, on three numbers you already have or can get: the hull’s remaining economic life, the duty cycle, and the cost of the next major overhaul or docking. A ten-year-old lighter with a sound hull and a short, regular route is a reasonable candidate to study for conversion. A twenty-five-year-old bunker tanker heading for a costly special survey is usually better replaced, and the replacement is what the 2030 rule will shape.
The mistake we see most often is treating fleet renewal as a single event. If three craft are due for replacement between 2028 and 2032, the ones after 2030 must meet the rule. Mapping every craft’s replacement date against 2030 now avoids ordering a boat in 2029 that is outdated on arrival. This is where an annual operating budget that carries a five-year capex view earns its keep.
MPA has also said it will consider other regulatory measures to move the sector away from fossil fuels. Nothing more has been published, but it is a reason not to assume today’s diesel craft will face no further requirements before 2050.
What changes for maintenance, crew and management
Electric and B100 craft change the maintenance plan more than the hull. A battery-electric boat swaps a large part of engine overhaul work for battery state-of-health tracking, thermal management, high-voltage system checks and fire detection around the battery space. Those tasks need to sit inside the planned maintenance system from day one, with clear intervals and the battery maker’s warranty conditions written in.
A B100 craft keeps a familiar engine room, but fuel handling changes. Biofuel brings its own concerns around storage stability, filter loading and seal compatibility, and the engine maker’s approval for B100 should be in writing before you rely on it. MPA said in April 2024 that blends up to B50 were already commercially available and that standards for up to B100 were expected by 2025, so check the current supply position with your fuel supplier.
Crew competency shifts too. High-voltage isolation, battery fire response and charging procedures are new skills for many harbour craft crews, and they belong in the familiarisation and drills programme alongside existing STCW and competency requirements. Class involvement is earlier as well, because battery systems and novel fuel systems are reviewed at design stage, which ties back into class survey preparation for the life of the craft.
The operator’s perspective: where owners get caught out
In our experience the risk is less the technology and more the sequencing. Owners sign a build contract, then find their base has no charger, or the berth’s power supply needs an upgrade that sits with a terminal operator on a different timeline. Check charging access and grid capacity before you sign.
The second trap is losing the operating data that would justify the decision. A sound electrification case is built on fuel consumption, running hours and route profiles per craft. If that data sits in paper logs, start capturing it now; real-time fleet monitoring makes the case far easier to build and to defend to a lender.
For bunker craft owners specifically, we would not rule out full electric, but we would expect B100 capability to be the more common route for tankers in the near term because of cargo pump loads and daily endurance. That is our interpretation, and it should be tested design by design. Our bunker vessel management work and the companion piece on bunker barge management cover the operating side of those craft in more detail.

Frequently Asked Questions
Do existing diesel harbour craft have to be replaced by 2030? No. The published requirement applies to new harbour craft operating in Singapore from 2030. Existing craft can keep operating, but the sector is expected to reach net zero by 2050 and MPA has said it will consider further regulatory measures.
What are the three options for a new harbour craft from 2030? A new craft must be fully electric, capable of using B100 biofuel, or compatible with net-zero fuels such as hydrogen. The owner chooses the pathway that fits the craft’s duty cycle.
What is TR 136? TR 136 is Singapore’s Technical Reference for electric harbour craft charging infrastructure and battery swap systems, published on 25 March 2025. It sets safety requirements and promotes interoperability, building on standards such as the Combined Charging System.
How much is the EASE grant for electric harbour craft? EASE covers part of the battery system cost, scaled to battery capacity and capped by vessel size, up to S$250,000 per vessel. It starts on 1 January 2027 and runs for two years.
Where can electric harbour craft charge in Singapore? The first pilot charger is at Marina South Pier, with a second due there. MPA has announced four chargers for Loyang Offshore Supply Base and public chargers at Jurong Port and West Coast Pier in 2027.
Quick Q&A
Should I order a diesel boat in 2029 to beat the deadline? Only if its economic life and resale value still make sense with a net-zero target in 2050 and the possibility of further rules. Run the numbers on a 2030-compliant alternative first.
Can my ship manager handle an electric craft? Ask whether they can show a battery maintenance plan, high-voltage crew training and class engagement at design stage. Those three are the test.
Is B100 a safe default for a bunker tanker? It is often the more practical route, but only with written engine maker approval and a confirmed fuel supply.
Planning your harbour craft renewal
Emaris Shipping manages tankers and bunker craft in Singapore, Malaysia and Indonesia, and we help owners plan fleet renewal around regulatory dates like 2030: mapping each craft’s replacement window, preparing the technical specification, and setting up maintenance and crew training for the new systems. See our ship management services and crew management and competency development, or contact us to talk through your fleet.