TL;DR: A ship management fee pays for the manager's people, systems and office: superintendents, crewing staff, the safety management system, accounts and purchasing. It does not pay for the ship. Crew wages, spares, stores, lubricants, repairs, dry-docking and insurance are operating expenses that the owner funds through an agreed budget, known as owners' account. Under BIMCO's SHIPMAN 2009 form the fee is a fixed annual sum paid monthly in advance, the budget is agreed separately, and the fee is reviewed every year. When you compare proposals, compare the scope behind the fee and the budget logic, not the headline number.
Most owners who feel surprised by their ship management costs were not overcharged on the fee. They misread what the fee was for. A ship management agreement separates two streams of money: the manager’s remuneration for running the vessel, and the vessel’s own operating costs, which the manager spends on the owner’s behalf. This article explains where that line sits, how the standard BIMCO SHIPMAN contract draws it, and which events should prompt a fee change.
What does a ship management fee actually pay for?
The fee pays for the manager’s own organisation, not for the vessel. In plain terms it buys the shore team and the infrastructure that technical, crew and safety management depend on.
For a technically managed tanker or bunker vessel, that usually means the assigned technical superintendent and their time, the crewing department that recruits, vets and rotates seafarers, the safety and quality team that runs the ISM Code system and the Designated Person Ashore (DPA) function, purchasing staff, accounts staff who produce monthly reports, and the office systems behind all of it, including the planned maintenance system (PMS) and document control. The SHIPMAN 2009 form puts it simply: the managers provide “their own office accommodation, office staff, facilities and stationery” at no extra cost to the owners.
What the fee does not cover is anything consumed by the ship. The fee is predictable and contractual; operating costs move with the vessel’s age, trading pattern and condition. For the full picture of what owners pay across both streams, see our guide to ship management costs explained.

How do lump sum, cost-plus and per-vessel fee structures differ?
There are three common ways to price management, and each puts risk in a different place.
A lump-sum fee is a fixed annual amount for a defined scope, paid in monthly instalments. Operating costs are passed through at cost against a budget. This is the SHIPMAN default and the most common structure for third-party technical management. The owner knows the fee, and the manager carries the risk of its own overheads.
A cost-plus arrangement reimburses the manager’s actual costs plus a margin or percentage. It appears more often in in-house or affiliated management and in project work such as newbuilding supervision or a major conversion. It is transparent on paper, but it rewards activity rather than outcome, so it needs strong audit rights.
A per-vessel-per-month rate is a lump sum expressed for fleet pricing, often tiered so the rate per ship steps down as the fleet grows. Ask what happens to the rate if one vessel is sold mid-contract.
Structure | How the fee is set | Who carries overhead risk | Where it fits | Watch for |
|---|---|---|---|---|
Lump sum (annual fee, paid monthly) | Fixed sum for a defined scope | Manager | Third-party technical or full management | Narrow scope definitions that push work into extras |
Cost-plus | Manager’s actual costs plus margin | Owner | Affiliated managers, project supervision | Weak cost control, audit access |
Per vessel per month (tiered) | Rate per ship, often stepped by fleet size | Manager, with fleet-size adjustment | Multi-vessel owners | Re-pricing when a vessel leaves the fleet |
Our view is that a lump sum with a tight scope schedule serves most small and mid-size tanker and bunker owners best. It gives the owner a fixed number to plan around and forces the scope conversation to happen before signing, which is when it should happen.
Inside the fee vs owners’ account
The cleanest way to read any proposal is to sort every cost into one of two columns. Owners’ account means the cost is paid from the owner’s funds, held by the manager in a separate account, and reported monthly.
Normally inside the management fee | Normally for owners’ account (operating expenses) |
|---|---|
Superintendent and fleet manager time within the budgeted attendance days | Crew wages, overtime, victualling and allowances |
Crewing department: recruitment, vetting, training records, rotation planning | Crew travel, visas, medicals and manning agency fees where agreed |
ISM safety management system, DPA function, internal audits | Spare parts, stores, chemicals, paints and lubricants |
Planned maintenance and purchasing administration | Repairs, class and statutory survey fees, dry-docking |
Monthly accounts, budget preparation and reporting | Hull and machinery, P&I and other insurance premiums |
Office accommodation, staff, IT and stationery | Port costs, agency fees and owner-requested vetting inspections |
Two items sit on the border and deserve a line in the contract. The first is superintendent attendance. Under SHIPMAN 2009, days used by the managers’ personnel beyond those agreed in the budget are charged at a daily rate stated in the agreement, and out-of-pocket costs such as travel and accommodation are reimbursed. The second is dry-dock project management. Some managers include it in the fee, others bill it as a separate project charge. Neither approach is wrong, but an owner comparing two proposals needs to know which one is which. Our article on what ship owners get wrong about technical management contracts covers more of these grey zones.
How SHIPMAN 2009 structures the fee, the budget and owners’ account
SHIPMAN 2009 is BIMCO’s standard ship management agreement and the form most third-party management contracts start from. It has a Part I of boxes, where the commercial terms are filled in, and a Part II of standard clauses. Three clauses do most of the money work. Clause numbers below follow the unamended 2009 standard form; signed contracts are often amended, so always read your own version.
Clause 12: Management fee and expenses
The owners pay an annual management fee stated in Box 14, payable in equal monthly instalments in advance. The fee is “subject to an annual review” by both parties. Office staff and facilities come at no extra cost. Out-of-pocket expenses properly incurred are reimbursed, and personnel days beyond the budget are charged at the Box 16 daily rate. If the owners lay the vessel up for longer than the period stated in Box 17, the fee is reduced for the excess period by an amount the parties agree, so the form sets a principle rather than a formula. Discounts and commissions the managers obtain while managing the vessel are, unless the agreement says otherwise, credited to the owners.
Clause 13: Budgets and management of funds
The initial budget sits in Annex C. Subsequent twelve-month budgets are presented “not less than three months before the end of the budget year”, and the owners must respond within one month. Once a budget is agreed, the managers estimate working capital and request funds each month for the following month, and the owners pay within ten running days. The money is held in a separate account to the owners’ credit. If the parties cannot agree a budget, either side may terminate on notice.
Clause 11: Income collected and expenses paid on behalf of owners
Money the managers collect for the owners is held in a separate account, and expenses the managers pay on the owners’ behalf remain payable by the owners on demand. This is the legal basis of owners’ account: the manager is spending the owner’s money as agent, not buying services and reselling them.
BIMCO released SHIPMAN 2024 in April 2024. It keeps the budget annex and fee schedule, separates a pre-delivery management fee from the annual management fee, and adds a cyber security clause, according to Haynes Boone’s review of the new form. Many existing contracts in this region still run on SHIPMAN 2009 or a manager’s own form based on it, so it remains the practical reference. The current BIMCO forms are listed on BIMCO’s SHIPMAN contract page.
What changes the fee, and what should trigger a review?
The fee should change when the work changes. SHIPMAN builds in an annual review, but four events justify reopening the number in between.
A change in fleet size is the first. Adding a vessel spreads overheads, and removing one concentrates them, which is why tiered rates exist. A change in scope is the second: moving from technical-only to full management, or adding commercial, insurance or vetting support, adds people and hours. Our comparison of full ship management vs technical management sets out what each scope involves.
Lay-up is the third. A laid-up vessel needs less management but not none, and the right reduction depends on whether she is in hot or cold lay-up and what preservation programme she follows. Our planned guide to hot vs cold lay-up covers what the manager still does. Sale or total loss is the fourth. Under SHIPMAN 2009 the agreement is deemed terminated on sale or total loss, and the owners pay a termination fee for the number of months stated in Box 19, unless the termination is caused by the managers’ default. Where the manager provides crew, the owners also continue to pay crew support costs for that period and an equitable share of severance costs, capped at the Box 20 amount. These numbers are negotiated, so agree them at the start rather than at the point of sale.
The operator’s view: where fee disputes really come from
In our experience, fee disputes rarely start with the fee. They start with an unclear scope schedule, then show up in the monthly accounts as an item the owner thought was included. The most common examples are superintendent attendance at a dry-dock or a vetting inspection, vetting preparation work, and extra reporting the owner adds after signing.
The fix is boring and it works. Write a scope schedule that lists services by name, state the number of budgeted superintendent days per year, and agree the daily rate for anything beyond them. Then tie the monthly report to that schedule, so the owner can see each owners’ account item against the annual operating budget line it belongs to. Performance terms belong in the same document. Our article on the ship management SLA covers how to write them.
One more opinion, stated plainly: a low fee paired with a vague scope is usually the most expensive option over a contract term. The savings on the fee are small next to what an under-resourced superintendent costs in unplanned off-hire, a failed inspection or a dry-dock overrun. If you are comparing ship management companies in Singapore, our ranked overview of ship management companies in Singapore and the ship management company checklist give you a structured way to compare more than price.

Frequently Asked Questions
What is included in a ship management fee? The fee covers the manager’s own services and overheads: superintendents, crewing staff, the ISM safety management system and DPA, purchasing, accounts and office systems. It does not include the vessel’s operating costs, which are paid from the owner’s funds against an agreed budget.
What is owners’ account in ship management? Owners’ account means a cost is paid with the owner’s money, held by the manager in a separate account and reported monthly. Crew wages, spares, stores, repairs, surveys, dry-docking and insurance are normally for owners’ account.
How is the management fee paid under SHIPMAN 2009? The standard form sets an annual management fee in Box 14, paid in equal monthly instalments in advance and reviewed annually by both parties. Extra superintendent days beyond the budget are charged at a daily rate stated in Box 16.
Does the management fee drop when a ship is laid up? Under SHIPMAN 2009, if lay-up lasts longer than the period in Box 17, the fee is reduced for the excess period by an amount the parties agree. The form does not set a formula, so the reduction should be negotiated before it is needed.
What happens to the fee if the vessel is sold? Under the standard form the agreement terminates on sale, and the owners pay a termination fee for the number of months stated in Box 19, unless the managers were at fault. Where the manager provides crew, crew support costs for that period and a capped share of severance costs may also apply.
Is SHIPMAN 2009 still used now that SHIPMAN 2024 exists? Yes. BIMCO released SHIPMAN 2024 in April 2024, but many contracts signed earlier, and many managers’ own forms, still follow the 2009 structure. Owners renewing a contract can ask which form the new agreement is based on.
Quick Q&A
Should I choose the manager with the lowest fee? Only if its scope schedule matches the others line for line. Compare budgeted superintendent days, what dry-dock supervision costs, and how owners’ account is reported before you compare the fee.
Can I see the manager’s margin on spares and stores? Under a SHIPMAN-style contract, spares and stores are bought for owners’ account and discounts are credited to the owner unless the contract says otherwise. Ask for audit rights and supplier invoices in the monthly accounts.
When is the right time to renegotiate the fee? At the annual review, and whenever the fleet size, scope, lay-up status or ownership of a vessel changes. If you are moving managers altogether, our ship management transition guide explains how to sequence it.
Talk to Emaris about scope before price
Emaris Shipping provides technical, crew and full ship management for tanker and bunker fleets in Singapore, Malaysia and Indonesia, with owners’ account kept separate and reported monthly. If you want a scope schedule and budget structure you can compare like for like, contact our team and we will walk through it with you.